Lost Creek Pump Station Update

The project, partnered with Ft. Bend LID#19, is approximately 70% complete.  The structure component is complete; the pumps and motors are set.  The contractor is working on the electrical and check valves.

The project is estimated to be completed by the end of the year.  Initial power will be supplied by generators, with the transition to grid power anticipated by February, 2026.

Lost Creek Pump Station Project Begins

The Ground Breaking Ceremony for the Lost Creek Pump Station was held August 6, 2024.

This is a joint project with Ft. Bend County LID 19 and MUD 115 and is expected to be completed in July, 2025.

Levee Raising Project Nearing Completion

The third segment of raising the FCLID levee is nearing completion this month, October, 2023 (ahead of schedule).

The contractor has brought in the select fill material from the neighboring District’s (FBC LID 2) Ditch “B” widening project and has filled the levee to the required height. As-built surveys of the levee top have been reviewed and all levee top elevations meet or exceed the required height. The contractor will be seeding the levee and cleaning up the site for his ultimate move out. We expect full completion of the project by the end of this month.

The levee raising project was completed in three segments, with the soils coming from two FCLID pond expansion projects and the FBC LID 2 project to complete the raising of the levee segments to at least the 500-year flood level of the Brazos River.