View Map
Ditch B project (north area of the District)
This project consists of excavation of additional detention in the pond adjacent to Sheffield Dr. in Lexington Colony and to address some channel erosion issues in the pilot channel.
The excavated material will be hauled to the east levee to raise that segment of levee approximately 2 feet.
Contractor: Texas Dewatering. Projected completion date is September 27, 2021
Pond A-2 and Ditch A-3 project (south area of District)
This project consists of excavation of additional detention in the smaller of the two lakes behind the Heritage Colony Rec Center and in the dry detention pond adjacent to Heritage Colony.
The excavated material will be used to raise the south levee approximately 2 feet. The project will also include addressing some lake edge erosion issues on the smaller lake and adding some concrete paving at the outfall structure to facilitate better maintenance access.
Contractor: Texas Rally Construction. Projected completion date is October 18, 2021