Hog Fences Installed Near Levee

In the past, the levees near the developing areas around Missouri City and Sugar Land have experienced severe hog damage. Trapping and removing/destroying the hogs proved to be a temporary solution due to the rapid breeding cycle of the hogs and the lack of natural predators in the area.

More recently, FCLID and a number of other levee districts have been treating their levees and ditches with insecticides, mostly to control ants (their beds/burrows can damage the levee surface and grass cover). An added benefit of that treatment is the reduction of grubs on our levees, which then reduces the occurrence of hogs rooting into the grass cover and damaging the surfaces of our levees and ditches. Without a food source, the hogs move on to other areas, unfortunately sometimes residents’ yards and common areas along the streets.

In 2023, FCLID partnered with neighborhoods and First Colony Community Services Association (FCCSA) to place fences near the levee to prevent hogs from entering neighborhoods. Large gates were installed for the sole use of FCLID for equipment access to the levee.  It is hoped this will reduce the hog damage in residential neighborhoods in the District.

Levee Raising Project Nearing Completion

The third segment of raising the FCLID levee is nearing completion this month, October, 2023 (ahead of schedule).

The contractor has brought in the select fill material from the neighboring District’s (FBC LID 2) Ditch “B” widening project and has filled the levee to the required height. As-built surveys of the levee top have been reviewed and all levee top elevations meet or exceed the required height. The contractor will be seeding the levee and cleaning up the site for his ultimate move out. We expect full completion of the project by the end of this month.

The levee raising project was completed in three segments, with the soils coming from two FCLID pond expansion projects and the FBC LID 2 project to complete the raising of the levee segments to at least the 500-year flood level of the Brazos River.

Project Continuation

June 22, 2023

Levee Raising Near Lake “A-2”

Since the completion of the Ditch “B” and Lake “A-2”/Pond “A-3” projects in mid-2022, the District has undertaken a third project to complete the raising of the levee just south of Double Lakes Dr.

The former projects did not produce enough excavated material to raise the entire levee.  This third project is in concert with an excavation project within FBC LID 2 and the District is using that material to raise the remaining portion of the levee.  Construction traffic will be accessing the site using the Double Lake driveway near the Heritage Colony Clubhouse.

The project began in late May and is expected to be completed by December, 2023.

Future Project Update

June 22, 2023

Joint Pump Station with LID 19

The District is participating with LID 19 and MUD 115 (Riverstone districts) in the construction of a second pump station along Steepbank Creek which will provide approximately 200,000 gpm additional pumping capacity for extreme rainfall events coincident with high Brazos River events outfalling into the Flat Bank Creek Diversion Channel.  The District undertook this joint project in lieu of adding a pump station inside of the District near the Lake “A-2” outfall into Steepbank Creek since an internal pump station would have necessitated pumping that water a second time from the LID 19 downstream system.

The project has recently received its environmental clearance from the Texas Water Development Board (TWDB).  The final electrical controls design is currently underway.  The project is expected to go into the bidding phase in late 2023 with construction expected to begin in early 2024.  The estimated construction time is 12-15 months.

What You Should Know About Hurricanes

From Ready.gov